Rooftop Recreation Areas

 

About ten years ago, the University of California San Diego's East Campus in La Jolla began considering an intriguing project.
The university originally envisioned a parking structure with more than 1,200 stalls on seven or eight levels. However, the project was to be built on a steeply sloping canyon site with unforgiving soil. Further complicating the build, the school wanted to build a soccer/athletic field immediately adjacent to the structure and wanted the building to keep a low profile due to the scenic and ecologically sensitive nature of the area.



This design-build project includes two parking structures with a total of 1,229 parking spaces on a steep hillside.

The winning design/build team—Bomel Construction Co. and International Parking Design— presented a plan to build two adjoining structures (instead of the owner's proposed single building), putting the soccer/athletic field on one roof to compensate for the larger footprint. This met the university's parking needs while allowing for a more-aesthetically pleasing facility, and stayed within the allocated budget
Completed in 2011, the end result is a two-level garage (called the East Structure) with 290,150 sq. ft. (428 parking spaces) and a rooftop synthetic-turf soccer field and archery range. The adjacent West Structure is five levels high, with 819 stalls and 216,000 sq. ft. Both are built with post-tension cast-in-place concrete.
The $24 million project is just one of the many unusual parking structures the Orange County, California concrete contractor has built in recent years. In the case of the UCSD East Campus project, the scope of construction involved much more than building two side-by-side, poured-in-place-concrete parking structures. Jay Smith, principal architect at UCSD says, "We threw a lot of curves at them. The adjacent medical center had a lot of scope that we had to add to the project without sacrificing the schedule."
The location of the canyon site, which is visible from the heavily traveled Interstate 5 freeway, was also a challenge.

Other members of the design-build team included Wolf Architecture, Hope Engineering, RBF Consulting, Syska Hennessey, PB&A and Spurlock-Poirier.
Cliff Smith, president of International Parking Design, says "If you tried to use the building to hold the earth back, the forces on the building would become greater than the seismic load, therefore the potential for the earth to push the building downhill is immense."
So instead they used soil-nails to hold the earth in place. They then poured a 40-foot-high retaining wall that runs 240 feet. In addition to being more seismically stable, this design allowed a light well to be created, bringing natural light into the structure."

Smith, at IPD, says a good working relationship between the key players was critical for project success. "Bomel was able to quickly establish that our designs were going to be within the budget set by the university," he said. "We have a great understanding of the way they work."
Despite the difficult conditions, numerous changes in the scope of work, and inovative rooftop practice field, the project was completed on time and within the established budget.
UCSD's Smith, who has been in the construction industry for 40 years, says "As busy as I am, I really appreciated Bomel's expediency."

"We ran into a number of unknown conditions, which tends to impact the schedule," he added. "In my experience, it could have thrown a lot of contractors for a loop and they'd ask for months and months of an extension. But Bomel didn't and got it all done professionally and maintained the schedule."

Rival East Coast High Schools Unite To Create One-Of-A-Kind Athletic Facility
In 2003, the New Jersey School Development Authority—a state agency that authorizes funding to special-needs districts—granted the Union City School District nearly $180 million to consolidate two aging but well-maintained high schools, Emerson and Union Hill, into one shiny new facility.
But where to build? Few options existed in Union City, considered the most densely populated municipality in the United States. The most logical piece of land—a two-block chunk owned by the district—was home to decrepit Roosevelt Stadium, which opened in 1937.
Faced with no other option than to demolish the stadium that hosted decades of games between the schools in an uptown/downtown rivalry, representatives from the school district and architectural firms HOK in New York and RSC Architects in Cliffside Park, N.J., came up with a novel plan: build a three-story school on the site but place a 2,200-seat synthetic-turf football, soccer and baseball stadium on top. The stadium's portion of the budget was $15 million.



Roosevelt Stadium is built on top of New Jersey's Union City High School. Directly below the artificial turf is a three-court gymnasium that seats 2,400 spectators, an auditorium, and the cafeteria.



The stadium has been nicknamed "Eagle's Nest" in honor of its new mascot, a soaring eagle. It seats 2,500 and has artificial turf.

Completed in 2010, Union City High School's Roosevelt Stadium—one of only a handful of rooftop athletic fields in the country—­stands as a tribute to its predecessor, with a classic grandstand roof, arched entries and the old facility's original signage. And, at three stories up, it may just offer the best seats in all of New Jersey.
"The views are incredible," says Jeannette Segal, a senior project manager at HOK. "They probably are the best of any high school stadium in the country. You can look out and see the Empire State Building."
The sideline grandstand holds 2,200 spectators, and there's room for another 1,800 temporary seats for football games in the baseball outfield.

Roosevelt Stadium, which also will meet some of the community's recreation needs, and the high-tech school itself represent an urban success story in one of New Jersey's poorest school districts, according to Union City School District superintendent Stanley Sanger.
At first glance the new Roosevelt Stadium appears similar to other large high school stadiums. But situated 28 feet off the ground, it has unique challenges and obstacles that Union City High officials are still learning to overcome. There is a 40-foot high net in each end zone to catch field goals and extra points. Since the first game in 2009, only two footballs and one soccer ball have been lost, according to Athletic Director Dave Clauser.

The facility is regularly at capacity, and draws other events as well. The Seattle Seahawks and San Francisco 49ers have both practiced at the stadium prior to games in New York.
This portion of the article was taken from the January 2010 issue of Athletic Business magazine. Reprinted with permission.